DAPHNE, Ala. — The Daphne City Council meeting on Monday included residents of Lake Forest and TimberCreek who wanted to ensure the council approved roadwork in their communities that has long been in planning stages.
The proposed roadwork for …
This item is available in full to subscribers.
Please log in to continue |
DAPHNE, Ala. — The Daphne City Council meeting on Monday included residents of Lake Forest and TimberCreek who wanted to ensure the council approved roadwork in their communities that has long been in planning stages.
The proposed roadwork for Lake Forest encompasses 1.42 miles from the entrance on Highway 90, up Bay View Drive and includes work on Ridgewood Drive and the Lawson Road entrance. A turning lane will be added on County Road 13 at the Lawson Road entrance. The proposed roadwork will include resurfacing, base repair, curbing and gutter installation.
Council members told the crowd the city should do what it requires other developers to do when making improvements to the city.
“I agree that we need to upgrade our roads, where appropriate, for curb and gutters to meet our city standards and I think that is what we are doing today and that is why we committed to the Complete Streets program,” Council President Cathy Barnette said.
We require builders and developers who come into the city and develop subdivisions to curb and gutter, so when the city comes back to redo a street should we not adhere to our own standards for other neighborhoods,” council member August Palumbo said.
Council member John Lake said considering the contributions Lake Forest has made to the city, the city can spend a few extra dollars to put curbs and gutters in the streets.
Engineers estimated the cost of the Lake Forest project to be $2.9 million, but the bid awarded to Hosea O. Weaver for $2,568,818. The total cost of the project is $3,050,818 and includes $240,000 for engineering costs and $240,000 for construction observation and testing costs.
Proposed roadwork for TimberCreek will include resurfacing and asphalt overlay with limited base repair, according to the resolution. The council announced at the meeting that roadwork should also include gutters and curbs.
The bid for TimberCreek road improvements has not been awarded, but estimated engineering costs for the project are $76,000. Bids received range from $278,072 to $392,387.
Funding for the Lake Forest project will come from various sources, including $500,000 from the fiscal year 2011 budget, $1,000,000 withdrawn from a hotly debated I-10 service road project and the remaining $1,308,818 will come from a transfer from the capital reserve fund.
Council member Ron Scott said he was uncertain where funding will come from for the rest of the road projects the city has planned.
“It has been a long time coming; we have worked hard for it. The mayor brought up some good points last week asking where we are going to get the dollars to continue the paving projects because we are roughly paving some 2.5 miles of a total six miles of road with Ridgewood and Bay View. Quite frankly, we don’t have any real answers. We have committed to half a million dollars a year for paving projects but there are a lot of streets around the city that also need help,” said Scott.
Barnette contended the Lake Forest road project will benefit the D’Olive watershed as well.
“The Lake Forest watershed is within the D’Olive watershed,” she said. “One of the recommendations was to improve our drainage systems with curb and gutter, which would actually help minimize some of our sediment pollution to our waterways. Although it is a road project we are getting some benefits for our watershed as well.”
Most of the public comment at the council meeting Monday touched on the road projects.
Council member Bailey Yelding said he is in favor of the road projects, but that repaving, curbing and guttering all the streets in Daphne that need it is not realistic.
“I realize the number of streets we have in Daphne that are not curbed and guttered so if we put in $3 million for two miles of curb and gutter will anybody in this building be here when we finish curb and guttering Daphne? No way,” Yelding said.
Also Monday, the council:
The council met in executive session to discuss pending litigation with the city attorney after adjourning the council meeting.
The next council meeting is set for 6:30 p.m. April 4 at City Hall on Main Street.